What are the safety operating procedures of Shenyang tamping machine? Do you know?
Preparation before going on the road:
Check whether all parts and components are completely intact and whether all fasteners of the foundation are loose according to the packing list. If they are loose and loose, they shall be tightened and matched. Check whether the effect of hand pump is outstanding; Check whether the oil inlet and outlet valves are tight and can be started only after confirming that they are normal. Check whether the lubricating oil reserve of internal combustion engine oil pan is within the scale range and add enough fuel. Check the hydraulic oil in the oil tank of the tamping machine and fill the hydraulic oil from the oil filler of the oil tank according to the rules of the oil gauge. The oil filling amount should be at the center of the upper hole of the oil window. During operation, the oil level shall not be lower than the red line of the lower hole of the oil window.
Precautions during operation:
Whether there is severe track lifting phenomenon when clamping ballast, so as to judge whether the operating oil pressure is too high. The operators of the two tamping machines shall pay close attention to the line conditions and cooperate closely to strive for coordinated action. Always pay attention to whether the sound of the diesel engine is normal and whether the fuel is burned dry. Stop the machine on the line and eliminate the fault.
Special safety rules:
Stop the machine on the line and eliminate the fault. In case of hydraulic system or engine failure during operation, the manual hydraulic pump shall be used to lift the pick and handle the failure immediately.
Other precautions:
When using in bridges, tunnels and station areas, the placement position of the lower track frame must be selected in advance. During the operation of the tamping machine, people shall not stand under the runway frame. Because the driving part of the tamping machine rotates at high speed, do not approach it with hands or body, and check the fastening condition of the rotating part regularly. If the single side approach is used, it is prohibited to get off the track in the central section of the double track. When using the tamping machine in small radius curve, pay attention to the dumping of the tamping machine.